On August 17, the first refitting project of floating production and storage tanker of Qidong COSCO Shipping Company, FPSO HELANG, was delivered to the shipowner and left the dock slowly.
Despite the grand naming ceremony on July 25, people are used to calling her "Rainbow".
The refitting project lasts for more than 8 months, involving the prefabrication and installation of nearly 5,000 tubes, the installation of 20,000 meters Tubing tubes, the laying and wiring of 280 kilometers of cables, the construction of five modules, the hoisting and integration of 15 modules and large-scale equipment, the MC inspection of 17012 ITRs, and the assembly and debugging of modules. Linked with the production plan, the node project is progressing in an orderly manner, and the project team strives hard to deliver on time.
The biggest challenge of Rainbow Steam Turbine Machinery is its heavy task and short time, which directly reduces the installation time in the field. It is April when the new installation project of the real tube installation began. The delivery time is only 3 months. A series of projects including installation, inspection, pump pressure, chemical cleaning and helium nitrogen experiment for more than 5,000 new pipes have been carried out.
A new "rainbow" travels on the waves, and it's gorgeous and colorful. New material technology construction and application, we pay great tribute to the heroes in front of the stage and behind the scenes once again!
This project is a cargo tanker refitted into FPSO LPG processing and storage project, into the ABS register! ABS project manager is Wang Zhixiang and COSCO quality project manager is Huang Kai, a senior quality engineer. Hu Kefeng is the general manager of the project.